Nepal Telecom (NT) is preparing to award the entire 10 million mobile
lines project to a single telecom equipment vendor against its original
plan.
The company, which assigned package B of the project to Huawei, is also set to award package A to same firm.
Officials at NT said despite reservations from some members, the NT
board recently decided to assign the package to Huawei, which is already
involved in 4.8 million lines (package B) of the 10 million lines
project. “We will issue a letter of intent within a week to Huawei,
informing other vendors that participated in the bidding,” said a senior
official.
According to the official, if other vendors do not object the decision,
NT will sealing a deal within a month. Huawei has quoted $122 million
for package A that, under which 5.2 million lines will be added in
Central, Eastern, Far Western and Mid-Western development regions.

NT had earlier planned to award the project to two vendors by breaking
it into two packages to ensure effective implementation and avoid
dependency on a single vendor. However, with other bidders ZTE
Corporation and Ericsson refusing to carry out the project for cost
reasons, NT was forced to approach Huawei.
Both ZTE and Ericsson had rejected package A even if they were legally
bound to accept it at the price quoted by Huawei, the lowest bidder. ZTE
and Ericsson had quoted $155 million and $242 million for 5.2 million
line’s package, respectively. As per tender condition, the second lowest
bidder ZTE was supposed to accept the project, and later, Ericsson too
refused to agree.
“It seems Huawei quoted less to bag both the packages, but we have no
option but to award it the package A,” said a member of the NT board,
sharing his past experience that NT had to ‘suffer a lot’ while
implementing 3.5 million lines through ZTE because of dependency on a
single vender. “Our original plan was to avoid such a situation again.”
In June, NT had signed a contract with Huawei for package B at Rs 6.74
billion ($85 million). The package enables the state-owned company to
add 4.8 million mobile lines having capacity
for 2G, 3G, and 4G in the Kathmandu valley and Western development region.
Guna Kesari Pradhan, NT spokesperson, said Huawei, as per the
agreement, would have to make a system ready to start distributing the
lines within a year from the singing of the contract. “Installation of
the core network under the first phase of package B has been completed
and network testing underway,” she said.
With NT losing its market share as a result of stiff competition from
private sector operator Ncell, the 10 million lines project is aimed at
aggressively its expanding services across the country. The current
system capacity of NT allows it to distribute only 5.5 million lines,
but more than 600,000 lines above the capacity have been
distributed.
Posted on: 2012-12-02 08:57(TheKathmanduPost)